Bundaberg Infrastructure Projects, QLD

Non-residential building approvals over the last 12 months are 0.52× this council’s own three-year average. Those approvals are $221.7m.

Named projects

24 projects.

TypeProposedActiveCompleted
Transport2612
Civic100
Energy010
Health010
Retail001

Largest stated values

Proposed

  1. Quay Street Upgrade, Bundaberg — Planning, $42m
    This project is expected to divert traffic away from Quay Street and around the CBD of Bundaberg.
    Start Late 2027 – Finish Early 2030
  2. Bargara replacement police facility — Announced, $17.5m
  3. Bargara Road Upgrade, Bundaberg — Planning, $10m
    This project is to upgrade targeted sections of Bargara Road, Bundaberg.

Active

  1. Branyan Street Crofton Street NORVILLE — Construction, $990.5k
    Reconfiguring the intersection to a single lane roundabout, providing a wombat crossing on all four legs to improve pedestrian connectivity and control vehicle speeds, providing.
    Start Jul 2025 – Finish Jun 2027
  2. Maryborough Street George Street BUNDABERG CENTRAL — Construction, $802.5k
    Upgrade traffic signals at the intersection, remove right turn filtering at the signalised intersection, bulb out verge to reduce signalised crossing widths, add pedestrian head.
    Start Jul 2025 – Finish Jun 2027

Completed

  1. Bonna Road, Branyan — Completed, $3.7m
    Bonna Road is a rural residential collector road with an existing width of 6.1m. This width does not meet Council's level of service based on road hierarchy and existing traffic.
    Start Mar 2023 – Finish Jun 2024
  2. Bucca Road, Bucca — Completed, $2.7m
    The existing timber bridge at the Bucca Road crossing of Hermans Gully is approximately 66 years old (constructed in 1957) and is now approaching end of life. Inspections of the.
    Start Aug 2023 – Finish May 2024
  3. Foleys Road, North Gregory — Completed, $1.6m
    Foleys Road has been triggered for rehabilitation based on the thresholds for roughness, rutting and cracking included in Council's Road Investment Strategy. Rehabilitation is.
    Start Oct 2023 – Finish Jun 2024
  4. Rosedale Road-Winfield Road intersection upgrade, Watalgan — Completed, $1.3m
    This project upgraded the intersection of Rosedale Road and Winfield Road at Watalgan.
    Start Mid 2023 – Finish Late 2023
  5. Ferry Hills Road, Wallaville — Completed, $839.2k
    Floodway has reached end of life. Requires replacement. Replace existing concrete floodway. Source of additional funds - Council.
    Start Sep 2025 – Finish Dec 2025

Other named projects