Southern Downs Infrastructure Projects, QLD

Non-residential building approvals over the last 12 months are 0.90× this council’s own three-year average. Those approvals are $23.7m.

Named projects

16 projects.

TypeProposedActiveCompleted
Transport0511

Largest stated values

Active

  1. Top Swanfels Road, Swanfels — Construction, $723.4k
    Road pavement is in poor condition with multiple failures and poor drainage. Roadside drainage works; make up material, granulate and seal.
    Start Oct 2025 – Finish Sep 2026
  2. Guy Street, Warwick — Construction, $695.7k
    Surface is fatigued and cracking. Asphalt pavement resurfacing, stormwater works, kerb & channel and footpath replacement.
    Start Jul 2025 – Finish Nov 2026

Completed

  1. Connells Bridge Road, Wheatvale — Completed, $2m
    Road damaged during the May 2022 flood event.Repairs and improved road surface resilience via concrete stabilised pavements on the bridge approaches.Total cost of proposed project.
    Start Jan 2024 – Finish Jun 2024
  2. Condamine River Road (Rural Road) — Completed, $1.9m
    Gravel bed level crossing frequently being washed away and requiring replacement, dangerous for drivers to traverse when water visibility is lowConstruction of a concrete bed.
    Start Aug 2023 – Finish Sep 2023
  3. East Street, Warwick — Completed, $1.5m
    Road pavement is in poor condition with multiple failures, cracking, damaged kerb and channel and insufficient drainage. Replace failed pavement with new imported material.
    Start Sep 2024 – Finish Jul 2025
  4. Freestone Road, Freestone — Completed, $1m
    Pavement has failed in many locations with many road depressions causing vehicles to unexpectedly rise/fallStabilise the pavement with a foamed bitumen treatmentTotal cost of.
    Start Feb 2024 – Finish Apr 2024
  5. Palmerin Street - Alice Street - WARWICK — Completed, $944.5k
    Standardise speed limit to 40 km/h along Palmerin Street, install wombat raised priority crossings on the Fitzroy and Percy Street roundabouts, zebra crossings at midblock.
    Start May 2024 – Finish Nov 2024
  6. Guy Street - Locke Street - WARWICK — Completed, $929.5k
    Standardise the speed limit to 40 km/h along Guy Street from Percy Street to Fitzroy Street and install wombat raised priority crossings on each leg of the Guy Street/Fitzroy.
    Start May 2024 – Finish Nov 2024
  7. Mount Marshall-Clintonvale Road, Mount Marshall — Completed, $718k
    Numerous defects in the pavementStabilise the pavement with a cementitious blend to renew the asset to its full life and provide increased resilience to future rain eventsTotal.
    Start Feb 2024 – Finish Apr 2024
  8. Glen Road Willi Street WARWICK — Completed, $529k
    Close Y-intersection of Glen Rd-Willi St, update signage and linemarking. Widen intersection of Glen Rd-Tooth St, install channelised turning lanes
    Start Jul 2022 – Finish Jun 2025

Other named projects